News

Report on EXEO Group’s First Series of Unsecured Bonds (Green Bonds)

July 31, 2023

1. Status of Appropriation of Proceeds of the Bonds (as of March 31, 2023)
EXEO Group used on July 15, 2022 all the proceeds of the bonds as funds for the construction of its woody biomass power generation facility, woody biomass gasification technology development, construction of the woody biomass gasification power generation facility, and construction of the solar power generation facility of an entity other than the Company.

(Note) The Mobara solar power generation facility is the facility of an entity other than the Company, and funds for construction used on behalf of the entity are accounted for as funds used. The construction cost to be paid by the entity will be deducted from the funds used, and unallocated funds will arise again.
(Total expenditure as of March 31, 2023 is 14,603 million yen.)

2. Environmental improvement effects (impact report)
All the facilities are under construction. (Since they have not started to operate, the environmental improvement effects are the anticipated effects.)

(Third-party evaluation of qualification)
Results of the Japan Credit Rating Agency (JCR)'s review of green bond evaluation after the issuance
https://www.jcr.co.jp/ratinglist/corp/1951


【本件に関するお問い合わせ先】
エクシオグループ株式会社 コーポレート・コミュニケーション室 広報担当
TEL:03-5778-1075 E-mail:contact@en2.exeo.co.jp